WILTON ROAD, RG30 2SS

Transformation in Progress

Purchase Price

£300,000

Stamp Duty & Legal Fees

£21,400

Date of Purchase

March 2025

Project & Build Investment:

Turn-Key Service Fees

£42,000

Professional & Statutory Fees

£12,000

Refurbishment & Build Costs

£140,000

Final Fit-Out & Furnishings

£30,000

Total Start-Up Cost

£224,000

Key Metrics

Estimated Current Value

£625,000

Estimated Gross Yield

10.98%

Estimated Cash-on-cash Return:

22.09% per annum

All Money Back in

approximately 4.5 Years

Gross Monthly Rental

approx. £4,950

Monthly Profit

approx. £1,809

Before

3 Beds | 1 Bath | 2 Receptions

Wilton Road Project started as a modest mid-terrace with a practical layout, but dated finishes and tired interiors had left the property looking and feeling ready for an update.

The ground floor included the entrance hall and staircase, dining area, fitted kitchen and
bathroom. Upstairs were three bedrooms with basic fittings, worn carpets and limited storage.

Gas central heating and uPVC double glazing were already in place, while a compact rear garden provided functional outdoor space.

The property offered a sound foundation, but its existing configuration and specification were not suited to modern shared living.

The opportunity was to make targeted improvements, rethink the layout and bring the property up to a more contemporary HMO standard.

After

6 Beds | 6 Baths | HMO

Wilton Project now presents as a modernised six-bedroom HMO, combining refreshed interiors with practical upgrades throughout.

A targeted refurbishment that transformed a tired mid-terrace into a refreshed, functional HMO for modern shared living.

Renovations Made

RPG took a targeted refurbishment approach, reworking the property into a 6-bed, 6-bath HMO configuration while focusing on practical improvements to layout, safety, comfort and presentation.

The works included:

Space reconfiguration

Selected openings and internal layouts adjusted to improve circulation and accommodate the new room configuration.

Fire & safety

FD30 fire-rated doors with intumescent strips, PIR emergency lighting and associated safety upgrades.

Building services

Radiators repositioned, additional sockets installed, lighting upgraded and plumbing works carried out.

Bedrooms

New flooring, decoration, electrical points and practical detailing throughout.

Communal areas

Kitchen and dining spaces refreshed with painted units, new worktops and updated lighting.

Bathrooms

Vanity units, mixer taps, towel rails and waterproof finishes introduced as part of the refurbishment.

Finishes

New carpets, laminate and vinyl flooring, plasterboarding, skimming and full decoration.

Final delivery

Snagging and finishing works completed to bring the property together as a cohesive HMO.

The result was a focused refurbishment that made better use of the property while significantly
refreshing its appearance, functionality and shared-living specification.

Before & After